Guide to Filling the Bill of Quantity (BoQ) for Malaysian Government Tenders

Guide to Filling the Bill of Quantity (BoQ) for Malaysian Government Tenders

By tenderpanel.com|07/12/2023
Last updated: 10/02/2025

Filling out a Bill of Quantity (BoQ) accurately is crucial for contractors bidding on government tenders. Errors or inconsistencies in the BoQ can result in disqualification, financial loss, or costly project overruns. This guide provides detailed, step-by-step instructions, practical examples, and expert insights to help construction company owners and estimators complete their BoQs correctly and competitively.


Step 1: Project Analysis and Tender Document Review

1.1 Analyze Tender Documents in Detail

Before preparing the BoQ, thoroughly study the tender documents, including the project specifications, scope of work, and technical drawings. Key areas to focus on:

  • Material Specifications: For example, if the project requires reinforced concrete Grade 40, confirm availability and pricing with suppliers before finalizing the BoQ.
  • Regulatory Compliance: Check requirements related to CIDB Malaysia, DOSH, and environmental regulations.
  • Project Timeline and Phasing: Understand the construction schedule to anticipate cash flow and material delivery timelines.

1.2 Conduct a Site Visit

A site visit is critical to validate the assumptions made in the tender documents. Important observations:

  • Site Accessibility: If a project site is located in a flood-prone area like Kelantan during monsoon season, factor in additional costs for drainage and protective measures.
  • Soil Conditions: A government road project in Sabah may require extensive ground stabilization if the soil has high clay content.
  • Utility Provisions: If the site lacks water or power supply, provisional costs for generators and water tanks should be included.

Step 2: Measurement and Quantification

2.1 Use Standard Methods of Measurement (SMM)

The Standard Method of Measurement (SMM) is essential for consistent and accurate calculations. Examples:

  • Concrete Works: Measured in cubic meters (m³) based on structural drawings.
  • Brickworks: Measured in square meters (m²) based on wall dimensions.
  • Steel Reinforcement: Measured in kilograms (kg) based on bending schedules.

2.2 Practical Measurement Examples

Example: Estimating Concrete for a Slab

  • A contractor is required to pour a 20m x 10m x 0.15m concrete slab.
  • Volume = 20 × 10 × 0.15 = 30 m³.
  • Include additional 5% waste factor = 31.5 m³.

Step 3: Itemization and Detailed Description

3.1 Write Precise and Clear Descriptions

Avoid vague descriptions. Compare:

  • "Steel reinforcement for columns" (Too generic)
  • "Mild steel reinforcement bars, Grade 500, 16mm diameter, 3.0m length, supplied and installed as per Drawing A2.2" (Detailed and actionable)

3.2 Assign Correct Item Codes and Categorization

Follow a systematic categorization using a BoQ numbering system:

  • Preliminaries (100): Mobilization, permits, site clearance.
  • Earthworks (200): Excavation, compaction, backfilling.
  • Concrete Works (300): Foundations, columns, beams, slabs.

This ensures consistency and easy reference.


Step 4: Pricing and Cost Estimation

4.1 Obtain Market Rates and Supplier Quotations

Prices for materials fluctuate due to economic conditions. Always obtain updated supplier quotations. For example:

  • As of 2025, BRC wire mesh (A7) costs RM6.50 per kg in Klang Valley but RM8.20 per kg in Sarawak due to logistics costs.

4.2 Factor in Overheads, Profit, and Contingencies

  • Overheads: Site security, machinery rental, temporary site offices.
  • Profit Margin: Typically between 10-20%, depending on competition.
  • Contingency (5-10%): Covers price volatility and unforeseen circumstances.

Step 5: Formatting and Organization

5.1 Structure the BoQ for Clarity

  • Use consistent units of measurement.
  • Follow government-prescribed BoQ formats (CIDB Malaysia guidelines).
  • Ensure logical sequencing (excavation before foundation, foundation before walls).

Step 6: Compliance and Final Review

6.1 Double-Check for Accuracy

Common errors to avoid:

  • Unit Mix-Ups: Ensure cubic meters (m³) are not confused with square meters (m²).
  • Misaligned Costs: Ensure materials pricing is consistent with supplier quotes.
  • Arithmetic Errors: Cross-check total BoQ costs with a spreadsheet tool.

6.2 Ensure Regulatory and Contractual Compliance

  • Verify that all BoQ entries adhere to Jabatan Kerja Raya (JKR) standards.
  • Ensure CIDB accreditation requirements are met for the specified contractor categories.

Step 7: Submission and Best Practices

7.1 Proper Documentation and Timely Submission

  • Submit the BoQ before the deadline along with required supporting documents.
  • Maintain copies of supplier quotations and cost breakdowns.

7.2 Common Pitfalls to Avoid

Overpricing or Underpricing: Overpricing may result in bid rejection, while underpricing may lead to financial losses. ❌ Neglecting Site Constraints: Failing to include costs for challenging site conditions can impact profitability. ❌ Ignoring Inflation Adjustments: Material price fluctuations can lead to cost overruns.

7.3 Pro Tips from Industry Experts

Leverage Digital Tools: Use cost estimation software like Buildsoft Cubit or Autodesk Quantity Takeoff to improve accuracy. ✅ Stay Updated on Market Prices: Follow CIDB Malaysia's Construction Cost Index for the latest material price trends. ✅ Maintain Good Supplier Relationships: Having multiple supplier contacts ensures better price negotiation and reliability.


Final Thoughts

Filling a BoQ is a meticulous process that requires accuracy, compliance, and market awareness. By following these detailed steps and leveraging real-world insights, construction companies can enhance their chances of securing government tenders profitably and sustainably.

For further assistance, visit tenderpanel.com, where we provide expert guidance on government tenders and contractor licensing.


Daftar & langgan untuk melihat senarai tender terkini